| Projects for 2008 | |||||
| 1. Coventry Rd-Cambridge Rd to Lingle Ave | |||||
| Overlay with 9.5mm, 2.0 inches thick - | |||||
| Estimated Cost | $5,914 | ||||
| 2. Cambridge Rd-Lingle Ave to Lingle Ave | |||||
| Overlay with 9.5mm, 2.0 inches thick - | |||||
| Estimated Cost | $106,422 | ||||
| 3. Barrington Rd-Yorkshire Rd to Cambridge Rd | |||||
| Overlay with 9.5mm, 2.0 inches thick - | |||||
| Estimated Cost | $22,467 | ||||
| 4. Yorkshire Rd-Barrington Rd to Lingle Ave | |||||
| Overlay with 9.5mm, 2.0 inches thick - | |||||
| Estimated Cost | $10,640 | ||||
| 5. Orchard Dr-Campbelltown Rd to Park Dr | |||||
| Overlay with 9.5mm, 1.50 inches thick - | |||||
| Estimated Cost | $10,454 | ||||
| 6. East Ridge Rd-N Forge Rd To Naftzinger Rd | |||||
| From N Forge Rd East 1900' (1/3 of the Length) | |||||
| Overlay with 9.5mm, 2.5 inches thick - | |||||
| Estimated Cost | $41,800 | ||||
| Total 2008 Road Projects | $197,697 | ||||